Sage MAS 90 and 200 ERP Product Update 6 (4.40.0.06) - Meterial Requirements Planning
Article Index
Page 10 of 17
Material Requirements Planning
- MRP Report for PD Item Est records, the Action by Date is now calculated correctly when the MRP Option ‘Build Time Calc for Make Items’ is set to ‘By Work Order Routing’.
- In MRP Auto Generate Work Orders, the correct component quantity is updated to Work Order Entry using the decimal precision chosen in CI Options Quantity.
- MRP Report, with MRP Option Build Time Calc for Make Items "By Work Order Routing", projected demands BC Item Est records no longer have a blank Required Date.
Tags: Product Update v4.40